CiTECH have won the order from Egyptian Maintenance Company to supply a total of Four Vertical Traditional WHRU with Integral By-pass for retrofitting existing WHRU currently running on site.

All Four units are designed to be cold case and to run wet. The units will be running on a regime of 3 duty and 1 x standby & will recover a total combined flow rate of 485,400 kg/hr and a total thermal duty of 33,000 kW through a Hot Oil System (Mobiltherm 605) from four Siemens SGT 500 Gas Turbines.