CiTECH won the order from Egyptian Maintenance Company to supply a total of Four Vertical Traditional WHRU with Integral By-pass for retrofitting existing WHRU currently running on site.

All Four units are designed to be cold case and to run flooded. The units will be running on a regime of 3 duty and 1 x standby & will recover a total combined flow rate of 485,400kg/hr and a total thermal duty of 33,000kwth through a Hot Oil System (Mobiltherm 605) from four Siemens SGT 500 Gas Turbines.

Project Info

Client:
Egyptian Maintenance Company
Owner/Operator:
Egypt Liquefied Natural Gas
Location:
Onshore Alexandria
Position:
31°13’52.2” Longitude 29°55’18.9” Latitude
WHRU Model:
Vertical Traditional with Integral By Pass
Qty:
4
Thermal Duty:
11,000kw th
Flow:
161,800 kg/hr